# How do I run database migrations safely in CI/CD?

> Add the column nullable, move the backfill to a separate throttled step, run migrations in their own stage, and drop the old column in a later release.

- Asked: 2026-06-11
- Answered: 2026-06-12
- Asked by: Melih
- Tags: ci-cd, veritabani, laravel
- Source: https://www.muhammetsafak.com.tr/en/just-ask/running-database-migrations-safely-in-ci-cd/
- Language: en-US
- Author: Muhammet Şafak

---
**Question:** In our CI/CD, `php artisan migrate` runs automatically between deployment steps. If a migration adds a column to a huge table and takes a while, the pipeline times out; or the old code that's live at that moment starts erroring because of the DB change.

How do I apply "backward-compatible migration" principles to the CI/CD flow on large projects?


Short answer: the real mistake is tightly coupling the schema change to the deploy while old code is still live — the fix is to **decouple** backward-compatible (expand/contract) migrations from the code deploy.

Let me name the problem: either old code meets the new schema and breaks, or a big `ALTER` locks the table and times out the pipeline. Both stem from the same root — coupling.

1. **Adopt the expand/contract discipline.** Don't add a column and deploy the code that needs it in the same release; never do it in the same release that uses a rename/drop. First add the column **nullable**, then deploy code that "writes to both old and new," and finally remove the old in a separate, later release.
2. **Take backfill out of the request path and the deploy step.** Do the work of filling the big table in a separate, **throttled** step — not inside the deploy step's transaction. Otherwise a single massive `UPDATE` both locks and times out.
3. **Make the migration its own pipeline stage, free of timeout pressure.** Move the schema change to a stage separate from app deploy. For big/locking changes, run them **out of band** with online-DDL tools like `pt-online-schema-change` / `gh-ost`; they add the column without locking the table.
4. **Write them idempotent and reversible, and gate the deploy on the migration.** Make migrations safe to re-run and reversible. Gate the deploy on the migration's success; but leave destructive steps (drop, rename) for a follow-up release after the new code is fully rolled out.

**Bottom line:** I'd make expand/contract a rule, decouple migrations from app deploy, and run big/locking changes off the critical path with online tools. Never do a schema change "mid-deploy while old code is live" — roll it out gradually and backward-compatible; then both the pipeline timeout and the old-code breakage disappear.

## Related Reading

- [How do I stop OPcache from causing 500s during a zero-downtime DeployerPHP deploy?](https://www.muhammetsafak.com.tr/en/just-ask/zero-downtime-deployment-with-deployerphp-and-opcache/) — Just Ask
- [How do I coordinate a zero-loss schema migration with dual-writing on a live table?](https://www.muhammetsafak.com.tr/en/just-ask/zero-loss-schema-migration-with-dual-writing-on-a-live-table/) — Just Ask